Planning permission is not normally needed when installing a biomass system in a house if the work is all internal. If the installation requires a flue outside, however, it will normally be permitted development if the conditions outlined below are met.

  • Flues on the rear or side elevation of the building are allowed to a maximum of one metre above the highest part of the roof.
  • If the building is listed or in a designated area even if you enjoy permitted development rights it is advisable to check with your local planning authority before a flue is fitted. Consent is also likely to be needed for internal alterations.
  • In a conservation area or in a World Heritage site the flue should not be fitted on the principal or side elevation if it would be visible from a highway.

If the project also requires an outside building to store fuel or related equipment the same rules apply to that building as for other extensions and garden outbuildings.

Find a Trade Professional

Use our partner directories from CIAT, FMB or RTPI to find an chartered architectural technologist, builder or planning consultant to help with your project or development.

Find a professional


Useful links

Make an application Planning consultancy calculator
    1. https://www.planningportal.co.uk/permission/common-projects/extensions
    2. https://www.planningportal.co.uk/permission/common-projects/outbuildings

    The Planning Portal is delivered by PortalPlanQuest Limited which is a joint venture between TerraQuest Solutions Limited and the Department for Levelling Up, Housing and Communities (DLUHC). All content © 2024 Planning Portal.

    The Planning Portal is delivered by PortalPlanQuest Limited which is a joint venture between TerraQuest Solutions Limited and the Department for Levelling Up, Housing and Communities (DLUHC). All content © 2024 Planning Portal.