The Penfold Review of non-planning consents, which was set up to identify whether non-planning consents delay or discourage investment, published its final report  in July 2010.  The Review was chaired by Adrian Penfold, Head of Planning and Environment at British Land.

The Government published its initial response to the review in November 2010 and indicated that the Planning Inspectorate would publish internal casework targets online and extend our annual statistical report to cover non planning consent work. These targets are included in the tables below.

Rights of Way

Public Path Orders

under section 257 of the Town and Country Planning Act 1990, or section 26, 118 or 119 of the Highways Act 1980

From Notice/Start date, to determination

Written Representations

80% within 27 weeks

Hearing

80% within 29 weeks

Inquiry

80% within 35 weeks

Acknowledge new Orders received

Within 5 working days

From Receipt, to Notice of the Start date

Within 10 weeks

 

Environmental

High hedges appeals
From Receipt, to Issue of decision

80% within 24 weeks

Hedgerow appeals

From Start date, to Issue of decision

80% within 28 weeks

Environment appeals

(Environmental Permitting, Waste Carriers, Water Abstraction and Anti-Pollution Works Notices)

From Start date, to Issue of decision

80% within 28 weeks*

* Unless an inquiry is expected to last 6 days or more, where a Bespoke timetable will be agreed with the parties

 

Commons

Approval of commons levy rates

From when figures are correct, to Approval

80% within 12 weeks

Commons Act 2006, section 16(6)

From Start date, to issue of decision

80% within 52 weeks

Commons Act 2006, section 38

No objections/in-house* decision

80% within 12 weeks

Objections/in-house decision

80% within 26 weeks

Decided by Inspector

80% within 52 weeks

Commons Act 2006 Part 1 (Regulation 27 referrals) No objections/in-house* decision 80% within 12 weeks
Decided by Inspector 80% within 52 weeks

Greater London Parks & Open Spaces Order 1967

No objections/in-house decision

80% within 12 weeks

Objections/in-house decision

80% within 26 weeks

Decided by Inspector

80% within 52 weeks

Land Acquisition Act 1981, section 19

 

To be confirmed

National Trust Act 1971 section 23

No objections/in-house decision

80% within 12 weeks

Objections/in-house decision

80% within 26 weeks

Decided by Inspector

80% within 52 weeks

* In house refers to decisions taken by officials on behalf of the Secretary of State